Update for week ending May 10, 2024
A printable version of our Weekly Project Updates is available.
Addition & Renovation, Blunt Hall
Laura Derrick, Project Manager
The level five (roof) concrete pour is complete. Penthouse steel scheduled to commence
next week. Demolition of the roof at the existing offices and stair tower is scheduled
to commence next week. Mechanical & electrical work continues at level zero, level
one, level two, and level three. Interior metal stud framing continues on level zero,
level one, level two and level three. Exterior metal stud framing continues. Domestic
water, electric, and steam shutdowns scheduled for this weekend to commence the new
restroom work. New restrooms on all floors scheduled to be complete for the fall semester.
Topping out is scheduled for May 22.
Autism Student Support Center, West Plains Campus
Adam Shuler, Project Manager
Steel installation is on-going and will be complete in a couple of weeks. Structural
stud framing will begin in the next week with the parapets and then exterior walls.
The roof installation will begin once the parapets are installed.
Addition & Renovation, Kemper Hall
Shanon Mitchell, Project Manager
A small area on the west side for the new training lab storage is being prepped for
concrete. Structural steel erection continues for the entire addition. Wall framing
to start next week. JQH Pkwy storm drain work to begin next week and continue for
two to three weeks.
Agricultural Innovation Hub, Darr Agricultural Center
Shanon Mitchell, Project Manager
Under slab electrical and plumbing work will be completed this week. Subgrade for
the concrete slab and termite treatment is complete. The 4” and 6” concrete building
slabs are scheduled to pour this week, and the 8” slab will pour next week.
Sidewalk Improvements, Springfield Campus
Laura Derrick, Project Manager
Sidewalk replacement to commence the week after graduation.
MSU Baseball Training Facility
Adam Shuler, Project Manager
The project is substantially complete.
Turf Replacement, Allison South Stadium
Eric Easter, Project Manager
Submittals have been reviewed and approved. The contractor is securing materials for
the project. Work will commence next week.
Renovate Locker Room, Hammons Student Center
Tanya Garretson, Project Manager
The clean-up of the north gym wall has been completed and the wall has received an
initial coat of primer and will receive paint in the coming week. More extensive work
in the north and south gyms and the east and west decks will begin following commencement.
Ongoing activities in the locker room and weight room include the installation of
hydronic water lines, electrical work, drywall finishing, and the installation of
hallow metal door frames.
Roof Replacement, Garst Dining Center
Eric Easter, Project Manager
Project submittals are being reviewed. The contractor is securing all of the materials
for the project. Work will commence next week.
Printable weekly updates
- May 10, 2024
- May 3, 2024
- April 26, 2024
- April 19, 2024
- April 12, 2024
- April 5, 2024
- March 29, 2024
- March 22, 2024
- March 15, 2024
- March 8, 2024
- March 1, 2024
- February 23, 2024
- February 16, 2024
- February 9, 2024
- February 2, 2024
- January 26, 2024
- January 19, 2024
- January 12, 2024