Weekly Project Updates

Header

Planning, Design and Construction is pleased to share weekly project updates with the campus and community. While not a comprehensive list, the updates reflect our more substantial campus projects. Below are our most current updates and previous updates are available at the bottom of this page.

If you would like additional details or information regarding a project not listed below, please contact our office at 417-836-5101 or email us at DesignAndConstruction@Missouristate.edu. Thank you for your interest in projects at Missouri State University.

Update for week ending May 10, 2024

A printable version of our Weekly Project Updates is available.

Addition & Renovation, Blunt Hall

Laura Derrick, Project Manager

The level five (roof) concrete pour is complete.   Penthouse steel scheduled to commence next week. Demolition of the roof at the existing offices and stair tower is scheduled to commence next week. Mechanical & electrical work continues at level zero, level one, level two, and level three. Interior metal stud framing continues on level zero, level one, level two and level three. Exterior metal stud framing continues.   Domestic water, electric, and steam shutdowns scheduled for this weekend to commence the new restroom work. New restrooms on all floors scheduled to be complete for the fall semester. Topping out is scheduled for May 22.

Autism Student Support Center, West Plains Campus

Adam Shuler, Project Manager

Steel installation is on-going and will be complete in a couple of weeks. Structural stud framing will begin in the next week with the parapets and then exterior walls. The roof installation will begin once the parapets are installed.

Addition & Renovation, Kemper Hall

Shanon Mitchell, Project Manager

A small area on the west side for the new training lab storage is being prepped for concrete. Structural steel erection continues for the entire addition. Wall framing to start next week. JQH Pkwy storm drain work to begin next week and continue for two to three weeks.

Agricultural Innovation Hub, Darr Agricultural Center

Shanon Mitchell, Project Manager

Under slab electrical and plumbing work will be completed this week. Subgrade for the concrete slab and termite treatment is complete. The 4” and 6” concrete building slabs are scheduled to pour this week, and the 8” slab will pour next week.

Sidewalk Improvements, Springfield Campus

Laura Derrick, Project Manager

Sidewalk replacement to commence the week after graduation.

MSU Baseball Training Facility

Adam Shuler, Project Manager

The project is substantially complete.

Turf Replacement, Allison South Stadium

Eric Easter, Project Manager

Submittals have been reviewed and approved. The contractor is securing materials for the project. Work will commence next week.

Renovate Locker Room, Hammons Student Center

Tanya Garretson, Project Manager

The clean-up of the north gym wall has been completed and the wall has received an initial coat of primer and will receive paint in the coming week. More extensive work in the north and south gyms and the east and west decks will begin following commencement.  Ongoing activities in the locker room and weight room include the installation of hydronic water lines, electrical work, drywall finishing, and the installation of hallow metal door frames.

Roof Replacement, Garst Dining Center

Eric Easter, Project Manager

Project submittals are being reviewed. The contractor is securing all of the materials for the project. Work will commence next week.

Printable weekly updates